Council Meeting: October 14th, 2025

 

Public Virtual Information Session

 

Date and Time: To be determined

 

Meeting link / ID: To be determined

 

Phone Number: To be determined

 

 

Project Development Status:

 

Pre-feasibility Stage: Completed

 

Planning Stage: Completed

 

Community Engagement: In-Progress

 

Municipal Support Resolution: In-Progress

 

Submission into LT2 (c-1) RFP: Dec’25

 

Indigenous Duty to Consult: To be determined

 

Environmental Assessment: To be determined

 

Interconnection Approvals: To be determined

 

Construction: To be determined

 

Milestone Date for Commercial Operation: May’30